← TenderDesk

Two worked examples

Both matrices were built from real, publicly downloadable Australian tender documents. Both tenders have closed. They are samples of the format and depth you get, not offers to those councils and not advice to any bidder. The bidder details in section A are fictional; every requirement and page reference is taken from the tender document.

1. Brewarrina Shire Council — T02-2026 Staff Housing (building, 41 pages)

Source: brewarrina.nsw.gov.au, Request for Tender Staff Housing 33 Bourke Street, retrieved 5 September 2026.

COMPLIANCE MATRIX
T02-2026 — Staff Housing, 27-33 Bourke Street Brewarrina
Buyer: Brewarrina Shire Council (ABN 22 6642 05362)
Closed: Friday 10 October 2025, 12:00 noon
Lodgement: tender box, post, fax or tender@brewarrina.nsw.gov.au
Contact: David Kirby, General Manager
Prepared by TenderDesk · worked example · assessment, not legal advice

Scope: construction and delivery of four two-bedroom modular homes or equivalent,
plus separately quoted four single car garages and Colorbond fencing per home site.

A. MANDATORY CONDITIONS OF PARTICIPATION — fail = not considered
------------------------------------------------------------------------------
#   Requirement                                    Source        Status  Gap
------------------------------------------------------------------------------
A1  Hold all accreditations, certifications,       Cl. 21.3      ?       Confirm NSW
    registrations and licences required at law     p. 11                 builder licence
    for the work                                                         covers modular
                                                                         and site works
A2  Compliance with the Building Code of           Cl. 21.3      ?       Confirm the
    Australia                                      p. 11                 modular design
                                                                         is BCA certified
                                                                         for the class
A3  Tender lodged by Closing Time and in the       Cl. 21.4      ✓       —
    prescribed manner                              p. 11-12
------------------------------------------------------------------------------
Note: this RFT states the participation conditions unusually briefly. Everything
else that can disqualify sits in the compliance criteria (B) and the contract
conditions (D), which is where bidders most often lose it.

B. DOCUMENTS THAT MUST ACCOMPANY THE TENDER
------------------------------------------------------------------------------
#   Document                                       Source        Status  Gap
------------------------------------------------------------------------------
B1  Tender Form, completed and signed              Tender Form   ✓
                                                   item 2(a)
B2  Schedule of Specialist Subcontractors          item 2(f)     ✗       Not yet
                                                   p. 16                 compiled
B3  Declaration re licences and registrations      item 2(g)     ✗       Needs current
                                                   p. 16                 licence numbers
B4  WHS Contractor Management System               item 2(h)     ✗       No documented
    Questionnaire                                  p. 16                 WHS system on
                                                                         file
B5  Floor plans, suggested three or more design    Advertisement ✗       Only one design
    possibilities                                  cl. 1.1 p. 2          currently drawn
B6  Details of PC items and allowances             cl. 1.1 p. 2  ?       Needs pricing
                                                                         breakdown
B7  At least two recent references for similar     cl. 1.1 p. 2  ?       One comparable
    work                                                                 project only
B8  Acknowledgement of all addenda                 item 2(i)     ✓
                                                   p. 16
------------------------------------------------------------------------------

C. EVALUATION CRITERIA — no weightings published
------------------------------------------------------------------------------
#   Criterion (cl. 21.2, p. 11)                    Evidence held      Gap
------------------------------------------------------------------------------
C1  Capability: technical and management           Two comparable      No CVs for the
    competence, financial viability, relevant      builds; no          nominated site
    skills, experience, availability of personnel  audited accounts    supervisor
C2  Opportunities for local employment and         None yet            Highest-value
    local business in the project                                      gap: name local
                                                                       subcontractors
                                                                       and suppliers
C3  WHS compliance and safe work methodology       Insurances only     No SWMS, no WHS
                                                                       system (links
                                                                       to B4)
C4  Plans submitted, program of works,             Design only         No construction
    achievement of outcomes sought by Council                          programme
C5  Overall cost and capacity to achieve maximum   Lump sum priced     Contingency for
    benefit within budget                                              transport not
                                                                       separated
C6  Technical merit                                Design only         —
C7  Degree to which the Tender meets the           Partly              B5, B6 open
    Principal's Requirements
C8  Risk assessment and awareness, particularly    None yet            No transport or
    during transportation and construction                             craneage risk
                                                                       assessment
------------------------------------------------------------------------------
Note: the RFT publishes no weightings. Council decides on "best value for money"
(cl. 21.1). Where weightings are absent, every criterion has to be answered as if
it carried equal weight; C2 and C8 are the two most often left blank by bidders and
both are named explicitly here.

D. CONTRACT OBLIGATIONS THAT AFFECT PRICE — read before you price
------------------------------------------------------------------------------
D1  Public Liability Insurance AUD 20,000,000 per occurrence, current for the
    whole contract period including the Defects Liability Period.   Cl. 3.12.1, p. 28
D2  Workers' compensation insurance for every person employed, and evidence that
    every subcontractor's employees are covered too.                Cl. 3.11, p. 28
D3  Insurance of the works at Contract Price plus 20%, covering Council, the
    contractor and every subcontractor, project and construction manager, held
    from tender acceptance through the Defects Liability Period.    Cl. 3.12.3, p. 28
D4  Professional Indemnity insurance is expressly NOT required.     Cl. 3.12.4, p. 28
D5  Principal Contractor duties: WHS management plan submitted to and approved by
    Council's Representative.                                       Cl. 3.16.1, p. 30
D6  Environmental management plan required.                         Cl. 3.13, p. 28
D7  Council may demand before acceptance: previous experience, plant and resources,
    a monthly cash flow schedule, all subcontractor names, and every priced
    submission received. Failure to supply in time makes the Tender informal.
                                                                    Cl. 24, p. 12
------------------------------------------------------------------------------

E. TOP THREE RISKS FOR THIS BIDDER
1. B4 / C3. No documented WHS management system. This is both a required submission
   and a scored criterion, so it fails twice. It is also the longest lead time item.
2. D1 and D3. Public liability at AUD 20m and works insurance at contract price plus
   20% must be confirmed with the broker before pricing, not after award.
3. C2. Local employment and local business is a named criterion in a small remote
   shire. A bidder with no local content answer is competing at a structural
   disadvantage regardless of price.

F. TIME REQUIRED
The WHS questionnaire, three design options, subcontractor schedule, references,
programme and risk assessment are the substantive work. Estimated 30 to 45 hours
for a bidder starting without a WHS system in place; roughly half that with one.
Latest sensible start: three weeks before Closing Time, because insurance
confirmations and subcontractor pricing are outside the bidder's control.

2. Coonamble Shire Council — TEN230531DJ (civil works)

COMPLIANCE MATRIX
TEN230531DJ — 987 REPA Flood Damage Road Repairs (Package 2)
Buyer: Coonamble Shire Council, NSW
Closed: 10:00 am, 31 May 2023
Contact: Dirk Jol, Manager Roads
Prepared by TenderDesk · worked example · assessment, not legal advice

A. EVALUATION CRITERIA — weightings published (cl. 1.7, p. 4)
--------------------------------------------------------------------------------
#   Criterion                     Weight  What it actually asks for      Gap
--------------------------------------------------------------------------------
A1  Price and financial benefit    40%    Lump sum cost                  —
A2  Experience and Capacity        25%    Past comparable contracts,     No referees
                                          operational AND financial      nominated; no
                                          capacity, staff qualifications, financials
                                          referees                       prepared
A3  Methodology                    15%    Approach to project outcomes   No mention of
                                          AND "relevance to Coonamble    local conditions
                                          Shire"                         in the method
A4  Management Systems             10%    WHS record and safety plans,   No documented
                                          Quality Management System,     QMS or EMS
                                          Environmental Management
                                          System
A5  Local Contractor               10%    Resident in the LGA, or pays   Bidder is from
                                          rates to it, or demonstrates   outside; no
                                          local purchasing, local        local content
                                          employment, local              statement drafted
                                          accommodation
--------------------------------------------------------------------------------

B. WHERE THIS BID IS ACTUALLY DECIDED
Price carries 40%, so a bidder assumes price decides it. It does not.
Price is a single number that every serious bidder lands within a few percent of.
The 60% that is left is written text, and three of those four criteria (A2, A4, A5)
are answered with documents the bidder either has or does not have. That is where
the spread comes from.

A5 deserves particular attention: 10% is available for local content, and the
criterion spells out exactly how an outside contractor can earn it — buying local
goods, hiring locally, renting local accommodation. A bidder who writes three
specific sentences here beats a bidder who writes nothing, at zero cost.
"The definition of what constitutes a local contractor is at the Principal's
discretion", so the answer has to be concrete, not a claim of intent.

C. PROCESS TRAPS IN THIS DOCUMENT
--------------------------------------------------------------------------------
C1  The tender briefing is NON-mandatory (cl. 1.4, p. 3) but requires
    registration by a stated deadline. Skipping it costs nothing formally
    and costs information practically.
C2  Site inspections are the tenderer's own responsibility (cl. 1.5, p. 3).
    Maps and photographic evidence are only available "on request" — a bidder
    who does not ask, bids blind on flood damage.
C3  The submission spans Volumes 1, 1a, 2 and 3 plus five appendices of rate
    schedules and three published addenda (cl. 1.2, p. 2). Incomplete
    returnable schedules are the most common avoidable failure.
C4  Decision date is fixed: Council meeting 15 June, acceptance letter 17 June
    (cl. 1.3, p. 3). Resource planning can be built on that.
--------------------------------------------------------------------------------

D. TOP THREE RISKS FOR THIS BIDDER
1. A4. No documented Quality and Environmental Management System. 10% of the
   score is unreachable without them, and they take weeks to produce.
2. A5. No local content answer. 10% available, costs nothing but writing.
3. C3. Volume 3 Returnable Schedules and the rate appendices are where an
   otherwise strong bid is ruled non-conforming.

E. TIME REQUIRED
Rate schedules and returnable documents: 12 to 20 hours. Written criteria (A2
to A5): 15 to 25 hours if the management systems exist, considerably longer if
they must be created. Latest sensible start: four weeks before closing.